You can't do that now, so you'll be able to walk around the entire stadium at both the main concourse and the upper level.
They're actually a little further along on this side of the stadium in terms of the steel construction.
Ultimately, all this comes up, all this steel is scheduled to be done by November,
So there will be work going on during the season.
That's one of the primary reasons.
There's actually the steel that will cantilever over the upper deck.
That's why we have to close the upper deck.
It just wouldn't be safe for people to be up there.
So that concourse will wrap in front of what is currently the club seat entrance.
Again, this is on the east side of the stadium.
And you can see these ramps are all in the process of being dismantled.
So this gets us back to where we are.
That's our office building that we moved in Monday, and that's the Four Seasons.
And behind that is the marina that I referenced a few seconds ago.
So we'll post this on our website.
Feel free to access it there.
OK, so let me let me turn to 2026, which is really some of the meat of what we're talking about today.
Remember that when we first laid out this construction plan.
We were going to be playing outside of Jacksonville for the 26th.