100% of those outside deep pile foundation elements will be completed by August.
So there's a lot of work that needs to get done between now and August.
There's actually six big cranes.
They call them crawler cranes because they actually move around as the work progresses, those cranes move.
So there's six of them actually in operation, both outside and inside the stadium.
One of the interesting things, this crane right here is our problem child, and at that one,
goes around the stadium this way and you get to a real pinch point.
So when you come back here, I guess in a few months, Ryan, you're gonna see that a large portion of the player parking lot here at the Miller Electric Center will be removed on a temporary basis.
The players then will park out here.
So that's moving along.
All of the structural steel will be completed by November.
There's 100 steel trusses that are being installed as we speak right now.
We opened up a big staircase by gate one earlier this year.
That was open for most of the season.
The second grand staircase is right behind us.
That'll open early during the 2026 season.
And then there will be similar staircases on all four corners of the stadium along with escalators that will run in tandem with the stairs.
The escalators will come
at a later date, before 2028, but they won't be this year.
The main concourse expansion is underway, and you can really begin to get a sense for how wide the concourse will be.