Mark Miller
speaker
9,705 appearances
61 recordings
4 series
first heard Sep 2023
last heard 5d ago
Mark Miller’s voice in public audio — every appearance, attributed to the second.
Trend
recordings per month · last 12 monthsRecordings per month over the last 12 months — 21 in all, peaking in Sep 2026 with 3.
Appearances
Loudoun County Planning Commission · Planning Commission Public Hearing - May 26, 2026 · 26 May 2026
meeting
We understand in any way that we can help up here further anything we do with the board to help make an application better, make it visually more appealing, I think we go a long way towards stemming some of the angst that applications like this will see when they go to the board.
That would be terrific.
Something like that would be great.
Thank you.
It's all gas.
That's mostly correct, but it is the water lines.
That's that area in between the trees and the substation.
There are two major water transmission lines that run through the site there, so that's kind of our limiting factor.
We can't go any closer to the trail.
commissioner miller thank you um i i support the the spirit of the motion which is that we need to send this forward to the board because the substation has to happen and i get that but i i am leery of sending it forward with the request to work on the design of the walls and the plantings and things in the buffering as it gets to the board i would prefer
If it's possible if it's the will of the Commission to keep this with us at a work session so that it gave us an opportunity We gave the minion opportunity to bring back to us some some thought into what walls and buffering could look like Because this is going to come up again and again And I think the more that we can do here will help
Dominion, NOVAC, any other utility, NextEra, wherever it's going to be in a couple years, to come before us with things that have taken that into consideration in advance.
And so if it's the will of the commission to send this forward and work on it as it gets to the board, great.
My preference would be to keep it here to go to work session.
so that Dominique could come back to us at some point in time and let us as a planning commission take a look at some of the things that they were proposing, some of the things we've proposed to them.
I sent Kathleen an email just recently, just now, with some of those designs I was mentioning before in my opening remarks.
So that's where I stand.
I certainly know that it needs to go forward, but I would like the opportunity for us as a commission to weigh in further on the design and the look of some of the buffering in the walls.
Thank you.
Aye.
Showing 1161–1180 of 9,705 · page 59 of 486
← Previous
Next →